Nalcor Energy Muskrat Falls Project Converter Station Soldier Pond, N.L., Canada

Mention of the industry
Energy

Areas of application
Protection and conversion of 230-kV lines

Catégories de produits
Protective panel and communication panel

Delivery date
March 2016 to December 2017

Goals and
characteristics


The project included the manufacture 19 protective enclosures, 10 control enclosures, and 8 communication panels, delivered in 3 phases.

Key elements of
the project


The project production deadline was very tight because of provisions in the contract with the client. The tests, programming, and full simulation of the system were conducted in our workshop with the end client present.